October 3rd 2005
Left: The tiles are being laid in the new kitchen. Middle: New tiles on the existing pool. Right: Glass is being installed in the reception area. |
 |
 |
 |
 |
 |
September 27th 2005
The tiling of the lobby and the walls are in the new pastry shop. |
September 15th 2005
Left: The pool and jacuzzi are taking shape, concrete will soon be poured. Middle: Buccaneers, the beach restaurant. Right: The Kids Club. |
 |
 |
 |
 |
September 14th 2005
The casting of the Quartermaster Deck continues today.
The roof on the band stand was changed.
Alan Armstrong Checks that the sewage system on the west of the property is working. This has already bean connected to the South Coast Sewage System. The earthling of the existing pool is almost complete. The preparation for the paving stones at the front of reception has begun |
 |
 |
 |
 |
September 7th 2005
The floor of the Quartermaster has started to be poured.
Please note the print design on the concrete. The new pool continues Roofing on the Hidden Treasure almost completed. |
 |
 |
 |
 |
 |
September 3rd 2005
Construction continues into September 2005.
The Sandy Bay Beach Resort begins to take shape. |
August 30th 2005
Left: Start of new pool and jacuzzi. Middle: The Kids Club Right: Buccaneers (beach café kitchen). |
 |
 |
 |
 |
 |
August 26th 2005
(Top Left) The base of the Kid's Club.
(Top Right) The reception area.
(Bottom Left) Excavation for the new pool.
(Bottom Middle) The new beach restaurant kitchen.
(Bottom Right) Manhole for the connection to the public sewage system |
 |
 |
 |
August 17th 2005
Work is progressing well.
The image on the right shows the plan of the new lobby at the Sandy Bay Beach Club.
CLICK ON THE IMAGE to view larger version of the Sany Bay Beach Club Lobby.
|
 |
 |
August 15th 2005
Work is progressing well.
This is a picture on the left is of work on the connection to the public sewage system. |
 |
 |
July 23rd 2005
Construction continues at the Sandy Bay Beach Resort Barbados. |
July 20th 2005
Left: This photo shows the first block being laid for the new Reception/Lobby area. Middle: This is the the weekly Project Team meeting. Right: The start of the Injection Well which takes care of all the drainage on the beach side. |
 |
 |
 |
 |
 |
Day 2
July 5th 2005
Construction continues at the Sandy Bay Beach Resort Barbados. |
 |
 |
 |
 |
 |
Day 1
July 4th 2005
The first day of construction of the Sandy Bay Beach Resort Barbados gets underway. |